QuestionPlease could you confirm (or maybe not) that statements such as "
the relevant PPE must be worn on site" and "
all gas installations to be carried out by CORGI registered personnel" do not really need to be included in the Pre Construction Plan, as a competent Contractor will already be aware of the legislation which covers such matters.
AnswerYou are correct.
The pre-construction h&s plan only needs to contain information about the project and any significant hazards that the designers have been unable to avoid.
It does not require to identify insignificant hazards that a competent contractor should be aware of. The issues that she raises are clearly site related ones that are the responsibility of the principal contractor.